Friday, October 15, 2010
The contractor is scheduled to work Saturday doing grading in preparation for installing curb and gutter, concrete driveways and sidewalk next week. Resident’s cars will need to be removed and parked on a side street between the hours of 7 AM and 5 PM. Concrete pouring is scheduled for Tuesday and residents on the west side of Indian will not have access to their driveways for approximately one week.