Friday, September 24, 2010
Water services and the sanitary sewer system have been completed. The contractor will continue storm sewer work into next week. The contractor is scheduled to begin preparation of the aggregate road base course the end of next week. Resident’s cars will need to be removed and parked on a side street between the hours of 7 AM and 5 PM.
Friday, September 17, 2010
Friday, September 10, 2010
The contractor is aiming to complete the water services this week or early next week. On Monday the contractor will begin concrete pavement removal in order to continue with sanitary sewer installation. Resident’s cars will need to be removed and parked on a side street between the hours of 7 AM and 5 PM.
Thursday, September 2, 2010
The water main chlorination reports have been received and water service installations should commence on Tuesday. Residents will be notified the morning of the shutoff for each home. The contractor has taken advantage of the dry weather over the past several weeks to work on the storm sewer in the low part of the street to the south and will continue replacing the sanitary main down the middle of the street along with sewer services.
Subscribe to:
Posts (Atom)