Friday, November 5, 2010
The contractor has completed the first lift of hot mix asphalt (binder course) this week. The contractor will work on hot-mix asphalt driveway aprons, topsoil placement, tree pruning and utility structure adjustments today and tomorrow. The contractor is scheduled to pave the final lift of asphalt (surface course) early next week.
Wednesday, November 3, 2010
UPDATE: Weather permitting, tomorrow, Thursday, November 4th, the contractor will be placing the first 2 lifts of asphalt on your street. The gravel ramps to your driveways will be removed today so that final grading can be completed. Parking is available on Indian north of Glenview Rd, Hunter Rd or Juniper during daytime work hours. No parking is permitted on the street from 7 AM to 6 PM.
Cars will be allowed in and out of the driveways once the asphalt has been placed and compacted. The street will still be open during paving for emergencies, deliveries, to drop off or pick up individuals, etc. If you must use the road, please do not leave vehicles unattended, it will only cause delays in the completion of the work.
The final top coat of asphalt will not be placed until the restoration work is done. You will again be notified when this work occurs.
Cars will be allowed in and out of the driveways once the asphalt has been placed and compacted. The street will still be open during paving for emergencies, deliveries, to drop off or pick up individuals, etc. If you must use the road, please do not leave vehicles unattended, it will only cause delays in the completion of the work.
The final top coat of asphalt will not be placed until the restoration work is done. You will again be notified when this work occurs.
Monday, November 1, 2010
Friday, October 22, 2010
The contractor is scheduled to install curb and gutter and concrete driveways on the east side of Indian next week. Resident’s cars will need to be removed and parked on a side street between the hours of 7 AM and 6 PM. Concrete pouring is scheduled for Tuesday and residents on the east side of Indian will not have access to their driveways for approximately one week. Paving of the first lift of hot mix asphalt (binder course) might be on Friday.
Friday, October 15, 2010
The contractor is scheduled to work Saturday doing grading in preparation for installing curb and gutter, concrete driveways and sidewalk next week. Resident’s cars will need to be removed and parked on a side street between the hours of 7 AM and 5 PM. Concrete pouring is scheduled for Tuesday and residents on the west side of Indian will not have access to their driveways for approximately one week.
Friday, October 8, 2010
Friday, October 1, 2010

Water services, sanitary sewer and storm sewer work will be complete this week (photograph - water main installation). The contractor is scheduled to begin preparation of the aggregate road base course next week. Resident’s cars will need to be removed and parked on a side street between the hours of 7 AM and 5 PM.